Milgard Tempering, Inc. v. Selas Corporation of America
902 F.2d 703 (9th Cir. 1990)

Hall, Circuit Judge:

    This appeal marks the end of nearly seven years of litigation over a "sure fire" glass tempering furnace purchased over ten years ago. The seller, Selas Corporation of America ("Selas") appeals the judgment of the district court awarding the buyer, Milgard Tempering, Inc. ("Milgard"), damages resulting from its failure to repair serious defects in the furnace. Milgard cross-appeals the district court's denial of attorneys fees. We have jurisdiction under 28 U.S.C. § 1291 (1988) and affirm.

I

    Milgard Manufacturing, Inc. ("Milgard Manufacturing") cuts and installs glass for use in residential construction. On June 11, 1979, it entered into a carefully-negotiated contract with appellant/cross-appellee Selas to purchase a horizontal batch tempering furnace. With Selas' consent, Milgard Manufacturing assigned the contract to appellee/cross-appellant, Milgard.

    Under the contract, Selas agreed to design and manufacture the furnace for $1.45 million. Its design was complex, and in Selas' eyes, experimental. However, Selas marketed it as a working piece of equipment. The contract provided a $50,000 bonus if Selas delivered all the major components before January 31, 1980. It also provided a penalty of $5,000 per week (not to exceed a total of $25,000) for every week of late delivery after March 31, 1980. Selas failed to meet either deadline, having completed delivery of major components in November, 1982.

    Selas agreed to assemble the furnace at Milgard's plant and to assist in a "debugging period" that both parties expected would end June or July 1980. The contract also required Selas, in a series of preacceptance tests, to demonstrate that the furnace was capable of achieving designated yield and cycle rates.   Section 28.5 of the contract limited Selas' liability for breach of warranty to repair or replacement of the furnace and barred liability for consequential damages. The parties modified the contract and agreed to forego the preacceptance tests and instead place the furnace in commercial production in July, 1980, thus making glass available for the "debugging" process.

    By January, 1982, Selas continued work on the furnace, but failed to achieve yield and cycle rates that substantially conformed with the contract specifications. Milgard then filed suit against Selas for breach of contract.

    In March 1982, the parties, without counsel, attempted to enter into a contractual agreement to settle the dispute. Under the proposed agreement, Selas would take over the tempering operation for 60 days to demonstrate the furnace's ability to achieve a 90% yield rate. It would also pay any operating losses Milgard incurred during that period. Then, if Milgard operated the furnace for six months without incident, Selas would "finetune" the furnace to achieve a 95% rate. Selas did the work and paid Milgard's operating losses. 

    Milgard dismissed the suit without prejudice. However, during the six-month period, the furnace failed to perform to the specifications of either the contract or the attempted settlement agreement.

    Milgard initiated a second lawsuit on March 4, 1983, alleging breach of contract and breach of warranty. On June 29, 1984, Judge Tanner in the district court granted summary judgment in favor of Selas. He found that the cap on consequential damages was a conscionable allocation of risk between sophisticated parties and therefore enforceable. He further held that the parties had reached an accord and satisfaction in March, 1982. The court awarded Selas the balance of the purchase price minus the delivery bonus. It also awarded Selas attorneys' fees under § 28.1(f) of the contract but denied fees to Selas' in-house counsel for time devoted to the litigation.

    This court, in Milgard Tempering, Inc. v. Selas Corp. of America, 761 F.2d 553 (9th Cir. 1985) [hereinafter Milgard I], reversed and remanded for trial. We held that the enforceability of the consequential damages limitation not only depended upon the conscionability of the provision when drafted, but upon the circumstances surrounding Selas' breach and inability to repair. Because these circumstances were disputed, we found summary judgment inappropriate. Id. at 556-57. We further noted that serious factual disputes surrounding the alleged accord and satisfaction required trial of that issue as well. We also vacated the award of attorneys' fees pending determination of the prevailing party at trial.

    On remand, after a five-week bench trial, Judge Bryan in the district court found that the furnace had never lived up to the specifications in the contract. He held that the limited repair remedy failed of its essential purpose and that Selas' default was sufficiently severe to expunge the cap on consequential damages. He awarded Milgard $1,076,268 in net damages. He also denied Milgard's claims for attorneys' fees.

    . . .

    Selas appeals the judgment and denial of its motion for new trial . . . . Milgard cross-appeals the denial of attorneys' fees. We affirm.

II

    Selas first argues that the district court erred in ruling that the limited repair remedy failed of its "essential purpose" and that such failure lifted the contractual cap on consequential damages.

A

    Section 28.5 of the contract limited Milgard's remedies in the event of breach of warranty to repair or replacement of the defective equipment. n4 Such limitations on a party's remedies are permitted by Washington's version of the U.C.C., Wash.Rev.Code § 62A.2-719(1)(a) (West Supp. 1989).

    An exclusive or limited remedy, however, must be viewed against the background of § 62A.2-719(2), which provides: "Where circumstances cause an exclusive or limited remedy to fail of its essential purpose, remedy may be had as provided in this Title." This section requires a court to examine the contract in general and the remedy provision in particular to determine what the remedy's essential purpose is and whether it has failed.

    A limited repair remedy serves two main purposes. First, it serves to shield the seller from liability during her attempt to make the goods conform. Second, it ensures that the buyer will receive goods conforming to the contract specifications within a reasonable period of time.

    A contractual provision limiting the remedy to repair or replacement of defective parts fails of its essential purpose within the meaning of § 62A.2-719(2) if the breaching manufacturer or seller is unable to make the repairs within a reasonable time period. Lidstrand v. Silvercrest Indus., 28 Wash. App. 359, 623 P.2d 710, 714 (1981). Accord Milgard I, 761 F.2d at 556. It is not necessary to show negligence or bad faith on the part of the seller, for the detriment to the buyer is the same whether the seller's unsuccessful efforts were diligent, dilatory, or negligent. See Wilson, 587 F.2d at 1375.

    The district court in this case found that the furnace had never lived up to the specifications of the contract.  Finding 23. Moreover, the court found that the few successful improvements were not made within a reasonable period of time, taking over two and one-half years. We agree that under these circumstances, the unreasonable delay and ultimate failure in repair made the repair remedy ineffective; thus, the remedy failed of its essential purpose.


B

    Washington courts have not addressed the issue of whether failure of a limited repair remedy may serve to invalidate a consequential damages exclusion. Therefore, it is our responsibility to determine how the state's supreme court would resolve it. In undertaking this task, we may draw upon recognized legal sources including statutes, treatises, restatements, and published opinions. Molsbergen v. United States, 757 F.2d 1016, 1020 (9th Cir.), cert. denied, 473 U.S. 934, 87 L. Ed. 2d 706, 106 S. Ct. 30 (1985). We may also look to "well-reasoned decisions from other jurisdictions." Takahashi v. Loomis Armored Car Serv., 625 F.2d 314, 316 (9th Cir. 1980). We review the district court's construction of Washington law de novo. See In re McLinn, 739 F.2d 1395, 1400 (9th Cir. 1984) (en banc).

1

    We begin our analysis with Fiorito Bros., Inc. v. Fruehauf Corp., 747 F.2d 1309, 1314-15 (9th Cir. 1984). In that case, we held that under Washington law, the failure of a repair remedy does not automatically remove a cap on consequential damages. We predicted that Washington courts would take a case-by-case approach and examine the contract provisions to determine whether the exclusive remedy and damage exclusions are either "separable elements of risk allocation" or "inseparable parts of a unitary package of risk-allocation". Id. at 1315 (quoting district court).

    If the exclusions are inseparable, we reasoned, a court's analysis should track the Official Washington Comments to § 62A.2-719(2) [hereinafter Washington Comments], which explain that the subsection "relates to contractual arrangements which become oppressive by change of circumstances . . . ." 747 F.2d at 1315. We then affirmed the district court's ruling that the seller's arbitrary and unreasonable refusal to live up to the limited repair clause "rendered the damages limitation clause oppressive and invalid." Id.

    Fiorito relied heavily on this circuit's analysis of Cal.Com.Code § 2719(2) (West 1964) in Wilson, 587 F.2d 1363. Wilson involved a contract between commercially sophisticated parties for a tunnel boring machine. The contract contained both a limited repair clause and a cap on consequential damages. After concluding that the repair remedy failed of its essential purpose within § 2719(2), this court held that the bar to consequential damages remained enforceable. We explained:

Parties of relatively equal bargaining power negotiated an allocation of their risks of loss. Consequential damages were assigned to the buyer, Wilson. The machine was a complex piece of equipment designed for the buyer's purposes. The seller Smith did not ignore his obligation to repair; he simply was unable to perform it. This is not enough to require that the seller absorb losses the buyer plainly agreed to bear. Risk shifting is socially expensive and should not be undertaken in the absence of a good reason. An even better reason is required when to so shift is contrary to a contract freely negotiated. The default of the seller is not so total and fundamental as to require that its consequential damage limitation be expunged from the contract.

Id. at 1375. However this court in Wilson quickly pointed out that its holding was limited to the facts and was in no way intended to state that consequential damages caps always survive failure of limited repair remedies. Id. at 1375-76.

2

    The district court in the instant case found Selas' default "fundamental, but not total." Nonetheless, it found the breach sufficiently fundamental to remove the cap on consequential damages. Selas claims that the court misunderstood the legal standard and that consequential damages may be allowed only when the seller's breach is both total and fundamental. n7

    We agree that the district court's characterization of the case law was flawed. n8 However, the analysis it employed was not. This court has found nothing magical about the phrase "total and fundamental" default in relation to U.C.C. 2-719(2). In Fiorito we eschewed such wooden analysis, leaving "each case [to] stand on its own facts." Id., 747 F.2d at 1314 (quoting Wilson, 587 F.2d at 1376). We further expressed our distaste for talismanic analysis in Milgard I, finding the "oppressive circumstances" analysis utilized by Fiorito and the Washington Comments and the "total and fundamental" default analysis in Wilson in accord with each other. 761 F.2d at 556.

    The task before the district court was to examine the remedy provisions and determine whether Seals' default caused a loss which was not part of the bargained-for allocation of risk. This was the analysis that the district court actually employed.

    We agree with the district court's decision to lift the cap on consequential damages. Milgard did not agree to pay $1.45 million in order to participate in a science experiment. It agreed to purchase what Selas represented as a cutting-edge glass furnace that would accommodate its needs after two months of debugging. Selas' inability to effect repair despite 2.5 years of intense, albeit injudicious, n9 effort caused Milgard losses not part of the bargained-for allocation of risk. Therefore, the cap on consequential damages is unenforceable.

III

    Next, Selas challenges the district court's determination of damages. The court had found that for 21 months (April 1, 1980 to December 31, 1982), the furnace was incapable of reaching any of the yield rates outlined in the contract. Thereafter, the furnace could reach a few with some regularity. Accordingly, the district court calculated damages for two time periods. First, it calculated Milgard's lost profits during the 21-month "damage" period. Second, it calculated losses Milgard did and would incur after December 31, 1982.

    In calculating the award for the damage period, the district court noted that Milgard earned an actual profit of $591,537 during that time. To determine what further profits Milgard lost during that period as a result of Selas' breach, the court used Milgard's production from January 1, 1983 to September 30, 1984 as a "benchmark" period. During that period, Milgard earned a net profit of $674,900. The court multiplied the benchmark figure by a factor of 1.5 and reduced the product to account for both depreciation of the furnace over its 11-year life span and losses caused by Milgard's own inefficient operation during the damage period. The resulting award for lost profits was $860,497.

    In determining damages incurred after December 31, 1982, the court drew upon testimony from Milgard's expert economist, Dr. Peter Finch. Dr. Finch estimated that the furnace's continued inability even to approach the specified cycle and yield rates did and would cause Milgard in excess of $300,000 in lost profits after that date. The court discounted parts of Finch's testimony, including his assumption that the furnace's useful life exceeded 11 years, and awarded Milgard an additional $252,608.

    Selas challenges both awards as speculative and unsupported by the evidence. Alternatively, it claims that the district court made a mathematical error in computing the lost profits for the damage period.

A

    The determination of damages is one of fact.  Thus, in accordance with Federal Rule of Civil Procedure 52(a), this court will not disturb an award of damages unless it is "clearly unsupported by the evidence," Roberts v. College of the Desert, 870 F.2d 1411, 1417 (9th Cir. 1988), or it "shocks the conscience." Brady v. Gebbie, 859 F.2d 1543, 1558 (9th Cir. 1988), cert. denied, 489 U.S. 1100, 109 S. Ct. 1577, 103 L. Ed. 2d 943 (1989).

    The basic test for recovery of lost profits was laid out in the seminal Washington Supreme Court opinion, Larsen v. Walton Plywood Co., 65 Wash. 2d 1, 390 P.2d 677, modified, 65 Wash. 2d 21, 396 P.2d 879 (1964):

[Lost profits] are properly recoverable as damages where (1) they are within the contemplation of the parties at the time the contract was made, (2) they are the proximate cause of defendant's breach, and (3) they are proven with reasonable certainty.

390 P.2d at 686 (citation omitted). The third element, dealing with certainty, "is concerned more with the fact of damage than with the extent or amount of damage." Alpine Indus., Inc. v. Gohl, 30 Wash. App. 750, 637 P.2d 998, 1001 (1981), opinion changed, 645 P.2d 737 (Wash.App. 1982) (quoting Gaasland Co. v. Hyak Lumber & Millwork, Inc., 42 Wash. 2d 705, 257 P.2d 784, 788 (1953)) (emphasis in original). This comports with the long-held view that a defendant should not profit from the difficulty in proving exact damages, particularly if his breach contributes to that difficulty.

    Until Larsen, Washington courts strictly applied the "new business" corollary to the lost profits rule: if the complaining party does not have a profit history prior to the period of damage, profits are denied as too speculative.  Concluding that strict adherence to this rule could produce unjust results, the Larsen court adopted the rule that "'lost profits will not be denied merely because a business is new if factual data is [sic] available to furnish a basis for computation of probable losses.'" 390 P.2d at 687 (quoting Barbier v. Barry, 345 S.W.2d 557, 563 (Tex.Civ.App. 1961).

    Expert testimony alone can provide a sufficient factual basis for an award of loss of profits. Alpine, 637 P.2d at 1001; Butcher, 581 P.2d at 1362. If the opinion of an expert provides a reasonable basis for inference, the court is freed from "the realm of uncertainty and speculation." Larsen, 390 P.2d at 687. Expert testimony must be based upon tangible evidence rather than mere speculation or hypotheses. Id. at 688. The court then must exercise its sound discretion in determining the amount of damages. Barnard v. Compugraphic Corporation, 35 Wash. App. 414, 667 P.2d 117 at 120 (1983). Cf. Long v. T-H Trucking Co., 4 Wash. App. 922, 486 P.2d 300, 303 (1971) (where difficult to ascertain what amount of loss was caused by defendant, trier of fact "must exercise a large measure of responsible and informed discretion"). Expert testimony with partial deficiencies may nevertheless support a finding of lost profits; the trier of fact is free to discount its weight accordingly, even if no evidence sustains the exact amount it awards. Alpine, 637 P.2d at 1002.

    All three tests for loss of profits have been met in this case. First, the district judge made the factual finding that the parties contemplated the possibility of lost profits. Because § 28.5 of the contract refers to such profits, this finding is not clearly erroneous.

    Second, the district court found that the failure of the machine to conform to the contract specifications proximately caused Milgard to lose profits. Selas does not challenge this finding and we do not disturb it.

    Third, the district court had a sufficient factual basis upon which to make its computation of lost profits. As forecast by Larsen and its progeny, Milgard's sole source of evidence in this area was its expert witness, Dr. Finch. Although the district judge found some of Dr. Finch's figures difficult to swallow, he pointed out that that did not negate them. Transcript at 3438. Consistent with Alpine, 637 P.2d at 1002, the court discounted the damage award in accordance with the weight of Finch's testimony. Finding 114. Therefore, we find no error.

. . .

    For these reasons, the judgment of the district court is AFFIRMED.