Resnick v. Uccello Immobilien GMBH, Inc.
227 F.3d 1347 (11th Cir. 2000)
Per Curiam:
Uccello Immobilien, GMBH ("Defendant"), seeks to reverse a
liquidated damages award ordered pursuant to a settlement agreement with Edward Resnick
("Plaintiff"), and to reverse the denial of a motion to extend the time of
performance. Because the liquidated damages award was punitive, and because the district
court did not abuse its discretion in denying the motion to extend time of performance, we
vacate in part and affirm in part.
A.
Plaintiff and Defendant entered into a settlement agreement to bring
Defendant's office building into compliance with the American with Disabilities Act
("ADA"), 42 U.S.C. § 12182, et seq. n2
The settlement required Defendant to begin construction for the accommodations 30 days
after the district court approved the settlement (subject to Defendant obtaining the
necessary building permits) and to complete the construction four months later. If
Defendant could not complete the project in a timely fashion due to circumstances beyond
its control, then Defendant would be afforded a reasonable delay upon agreement of the
parties or by court order. Otherwise, delay in completion would result in liquidated
damages of $100 per day plus costs and fees.
On 4 December 1997, the district court approved the settlement and
retained enforcement authority. Defendant did not apply for a building permit until
August 1998. When Plaintiff visited the building in January 1999, he observed that the
accommodations required by the settlement had not been completed; Plaintiff, however, was
still able to transact his business in the building. At Plaintiff's request, an ADA
consultant then inspected the building to confirm which accommodations required by the
settlement remained incomplete.
Plaintiff on 2 March 1999 filed a Motion to Enforce the Settlement
against Defendant. After filing four extensions to reply to Plaintiff's motion, Defendant
responded in June 1999, at which time Defendant also moved to enlarge the time to satisfy
the settlement.
The district court ordered Defendant to complete the accommodations, to
pay Plaintiff's attorney's fees and costs, and to pay liquidated damages of $18,500.00 n3 to a charity as designated by Plaintiff. The court also
denied Defendant's motion for an extension of time to complete the accommodations.
Defendant now appeals.
B.
We review a court's decision to enforce
a settlement agreement for an abuse of discretion. An error of law is an abuse of
discretion per se. Principles governing general contract law apply to interpret
settlement agreements. And, even though this settlement agreement arose under the
ADA, state contract law directs our analysis here.
Liquidated damages arising from breach of
contract are appropriate when (1) damages from the breach are not readily ascertainable,
and (2) the sum stipulated is not grossly disproportionate to the damages reasonably
expected to follow from the breach. MCA Television Ltd. v. Public Interest Corp.,
171 F.3d 1265, 1271 (11th Cir. 1999); Hyman v. Cohen, 73 So. 2d 393, 401 (Fla.
1954) (en banc ). But liquidated damages are inappropriate when they serve only
to punish the breaching party. Lefemine v. Baron, 573 So. 2d 326, 328-29 (Fla.
1991).
For the first element, potential damages arising from breach of this
settlement agreement are not readily ascertainable. Handicapped persons who are
inconvenienced or harmed by Defendant's failure to comply with the settlement agreement
may suffer some damage of varying degrees from Defendant's potential breach of contract. Thus, some amount of liquidated damages
might be appropriate in this context.
The amount of liquidated damages provided by the settlement agreement,
however, is grossly disproportionate to the damages reasonably expected to flow from the breach. While liquidated damages
may or may not precisely compensate for the actual breach, the disparity may not be so
great as to compensate minimal damages with substantial sums. See MCA Television Ltd.,
171 F.3d at 1271 ("Parties may not [] use [liquidated damages] provisions as a way to
secure for themselves greater damages in the event of a breach than contract law would
normally allow.").
In this case, Plaintiff entered the building in January 1999 and saw
that the settlement requirements had not been met; he seemingly was not denied use of the
building based on his handicap and was still able to complete his business there.
Plaintiff has not alleged that he suffered monetary damages due to the breach; yet he
seeks to enforce a $18,500 liquidated damages award. Absent the liquidated damages
provision, Plaintiff would be entitled to minimal damages at best for the breach. The
gross disparity between the stipulated amount of liquidated damages and the damages
flowing from the beach causes the damages provision to fail.
That the district court ordered the damages award to be paid to a
charity as directed by Plaintiff further establishes that this award was punitive and that
Plaintiff suffered no actual damages from the breach. Plaintiff seeks no personal
compensation for the breach; payment to the charity serves only to penalize Defendant for
nonperformance, much like payment to a public entity for violation of a local ordinance.
Plaintiff and the district court rely on Six Cos. of Cal. v. Joint
Hwy. Dist. No. 13, 110 F.2d 620 (9th Cir.), rev'd on other grounds, 311 U.S.
180, 61 S. Ct. 186, 85 L. Ed. 114 (1940), to argue that liquidated damages may be awarded when the breach
inconveniences a group intended to benefit from the contract. In that case, the court
awarded a municipality liquidated damages under a contract to build a highway and tunnel.
The court held that, even where a municipality suffers no actual damages from the breach, liquidated
damages are available for the "inconvenience and loss which will flow to its
inhabitants for whose benefit the improvement is intended and at whose cost it is to be
built." Id. 110 F.2d at 625.
Six Cos. of Cal. is inapplicable to and distinguishable from
the present facts. This contract does not involve a public entity, but instead a private
charitable organization and disabled persons. Unlike public funds used to construct
a major highway, the intended beneficiaries (disabled people who are denied access to
Defendant's building) under the contract are not paying for the improvements. In addition,
Plaintiff has not asserted that he has even been inconvenienced or suffered loss from the
breach. See Multitech Corp. v. St. Johns Bluff Investment Corp., 518 So. 2d 427,
433 (Fla. 1st DCA 1988) (finding it inequitable to enforce liquidated damages for breach that "bore no significance to the
[plaintiff]").
Liquidated damages are permissible where the
award is intended as compensation for failure to perform. The liquidated damages provision
at issue here, however, is a penalty intended to induce performance of the settlement
agreement. The settlement agreement does not apportion liquidated damages based on the
different accommodations not completed; Defendant is subject to the same penalty whether
substantial or only minor improvements are incomplete. Even Plaintiff in his filings
refers to the liquidated damages clause as a penalty.
We vacate the award of liquidated damages because the award is grossly
disproportionate to damages reasonably expected to flow from the breach and is solely
punitive.
C.
The district court did not abuse its discretion in denying Defendant's
motion to extend the time for performance. . . .
D.
Pursuant to the terms of the settlement agreement, the district court
properly awarded Plaintiff, as the prevailing party, attorney's fees, costs and expert
fees incurred in litigating at the district court. The settlement agreement entitles
the prevailing party in an enforcement action to an award of such fees. Notwithstanding
our decision to set aside the award of liquidated damages, we affirm the district court's
decision to award fees and costs for the proceedings in district court.
We remand to the district court to determine the appropriate amount of fees
and costs to be awarded to Plaintiff.
VACATED in part, AFFIRMED in part, and REMANDED.
Roney, Circuit Judge, dissenting:
I respectfully dissent. I would affirm the district court's decision.
To us who are fully able, it may seem that a disabled person suffers
minimal damage when a building does not conform to the legal requirements, but for the
person whom those regulations seek to protect, the harm may be far more than minimal.
Obviously this is virtually impossible to quantify in economic terms. That is the exact
reason that the law provides for liquidated damages. Otherwise there is no way to enforce
compliance.
The appellant made an agreement. There is no just reason why it should
not pay damages for failure to fulfill the terms of that agreement. Certainly, if the
requirement was in the form of a mandatory injunction rather than a settlement agreement,
the assessment of the minimal amount here for violation of that injunction would not be
questioned by this Court. Although this is an individual case, not a class action, the
settlement agreement was intended to benefit others than the plaintiff and it seems to me
the district court's decision should be reviewed with that in mind.