Rockingham County v. Luten Bridge Co.
35 F.2d 301 (4th Cir. 1929)
Parker, Circuit Judge. This was an action at law instituted in the
court below by the Luten Bridge Company, as plaintiff, to recover of Rockingham county,
North Carolina, an amount alleged to be due under a contract for the construction of a
bridge. The county admits the execution and breach of the contract, but contends that
notice of cancellation was given the bridge company before the erection of the bridge was
commenced, and that it is liable only for the damages which the company would have
sustained, if it had abandoned construction at that time. The judge below refused to
strike out an answer filed by certain members of the board of commissioners of the county,
admitting liability in accordance with the prayer of the complaint, allowed this pleading
to be introduced in evidence as the answer of the county, excluded evidence offered by the
county in support of its contentions as to notice of cancellation and damages, and
instructed a verdict for plaintiff for the full amount of its claim. From the judgment on
this verdict the county has appealed.
. . .
Coming, then, to the third question -- i. e., as to the measure of
plaintiff's recovery -- we do not think that, after the county had given notice, while the
contract was still executory, that it did not desire the bridge built and would not pay
for it, plaintiff could proceed to build it and recover the contract price. It is true
that the county had no right to rescind the contract, and the notice given plaintiff
amounted to a breach on its part; but, after plaintiff had received notice of the breach,
it was its duty to do nothing to increase the damages flowing therefrom. If A enters into
a binding contract to build a house for B, B, of course, has no right to rescind the
contract without A's consent. But if, before the house is built, he decides that he does
not want it, and notifies A to that effect, A has no right to proceed with the building
and thus pile up damages. His remedy is to treat the contract as broken when he
receives the notice, and sue for the recovery of such damages, as he may have sustained
from the breach, including any profit which he would have realized upon performance, as
well as any other losses which may have resulted to him. In the case at bar, the county
decided not to build the road of which the bridge was to be a part, and did not build it.
The bridge, built in the midst of the forest, is of no value to the county because of this
change of circumstances. When, therefore, the county gave notice to the plaintiff
that it would not proceed with the project, plaintiff should have desisted from further
work. It had no right thus to pile up damages by proceeding with the erection of a useless
bridge.
The contrary view was expressed by Lord Cockburn in Frost v. Knight, L.
R. 7 Ex. 111, but, as pointed out by Prof. Williston (Williston on Contracts, vol. 3, p.
2347), it is not in harmony with the decisions in this country.The American rule and the
reasons supporting it are well stated by Prof. Williston as follows:
"There is a line of cases running back to 1845 which holds that, after an absolute repudiation or refusal to perform by one party to a contract, the other party cannot continue to perform and recover damages based on full performance. This rule is only a particular application of the general rule of damages that a plaintiff cannot hold a defendant liable for damages which need not have been incurred; or, as it is often stated, the plaintiff must, so far as he can without loss to himself, mitigate the damages caused by the defendant's wrongful act. The application of this rule to the matter in question is obvious. If a man engages to have work done, and afterwards repudiates his contract before the work has been begun or when it had been only partially done, it is inflicting damage on the defendant without benefit to the plaintiff to allow the latter to insist on proceeding with the contract. The work may be useless to the defendant, and yet he would be forced to pay the full contract price. On the other hand, the plaintiff is interested only in the profit he will make out of the contract. If he receives this it is equally advantageous for him to use his time otherwise."
The leading case on the subject in this country is the New York case of Clark v. Marsiglia, 1 Denio (N. Y.) 317, 43 Am. Dec. 670. In that case defendant had employed plaintiff to paint certain pictures for him, but countermanded the order before the work was finished. Plaintiff, however, went on and completed the work and sued for the contract price. In reversing a judgment for plaintiff, the court said:
"The plaintiff was allowed to recover as though there had been no countermand of the order; and in this the court erred. The defendant, by requiring the plaintiff to stop work upon the paintings, violated his contract, and thereby incurred a liability to pay such damages as the plaintiff should sustain. Such damages would include a recompense for the labor done and materials used, and such further sum in damages as might, upon legal principles, be assessed for the breach of the contract; but the plaintiff had no right, by obstinately persisting in the work, to make the penalty upon the defendant greater than it would otherwise have been."
. . . It follows that there was error in directing a
verdict for plaintiff for the full amount of its claim. The measure of plaintiff's damage,
upon its appearing that notice was duly given not to build the bridge, is an amount
sufficient to compensate plaintiff for labor and materials expended and expense incurred
in the part performance of the contract, prior to its repudiation, plus the profit which
would have been realized if it had been carried out in accordance with its terms.
. . . The judgment below will accordingly be reversed, and the
case remanded for a new trial.
Reversed.